How are defined inventory levels (such as minimum inventory requirements) considered when running the Material Requirements Planning (MRP) wizard?

How are defined inventory levels (such as minimum inventory requirements) considered when running the Material Requirements Planning (MRP) wizard?
A . Suppty
B . Recommendations
C . Demand
D . Stock on Hand

Answer: A