From whom does a Team Manager obtain approval for a completed product?

From whom does a Team Manager obtain approval for a completed product?
A . Project Manager
B . Project Support
C . The authority defined in the Product Description
D . Senior Supplier

Answer: A

Explanation:

In the PRINCE2® methodology, the Team Manager obtains approval for a completed product from the Project Manager. The Project Manager is responsible for ensuring that the products delivered by the Team Managers meet the project’s standards and requirements before accepting them.

Reference: PRINCE2® Foundation official documentation and study materials.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments