Free float is the
Free float is the
A . Difference between the early dates and late dates of an activity.
B . Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.
C . Difference between the early finish dates and late finish dates of an activity.
D . Difference In float value of the critical path activities and the float value of the specific activity being analyzed.
Answer: B