For which objects can you perform budget availability control? (Choose two.)

For which objects can you perform budget availability control? (Choose two.)
A . Internal Order
B . Profit Center
C . Project
D . Cost Center

Answer: A,D

Explanation:

Reference: https://blogs.sap.com/2019/12/24/budget-availability-control-for-cost-centers-in-sap-s-4hana-1909/