Exam4Training

For the purpose of transparency when does Scrum say a new Increment of working Software must be available? (choose the best answer)

For the purpose of transparency when does Scrum say a new Increment of working Software must be available? (choose the best answer)
A . Before the release Sprint.
B. When the Product Owner asks to create one.
C. Every 3 Sprints.
D. After the Acceptance Testing phase.
E. At the end of every Sprint.

Answer: E

Latest PSD-I Dumps Valid Version with 166 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version