Explain how the above mentioned report may differ from a report that you produce for the project manager, who is a test specialist Select TWO items from the following options that can be used to report to the project manager and would not be included in a report to senior management. 1 credit
A . Show details on effort spent
B . List of all outstanding defects with their priority and severity
C . Give product risk status
D . Show trend analysis
E . State recommendations for release
Answer: A,B