What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

You are installing new copper cabling. What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?A . Pre-terminated cabling is already factory tested and saves installation time.B . There is no advantage as most new copper cabling network designs are based on category 3 or 5E...

March 29, 2025 No Comments READ MORE +

What should you recommend?

You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%. What should you recommend?A . Review the cable lengths of each UPS to the common busbarB . Nothing, there is no reason for any concernC . Review the common...

March 26, 2025 No Comments READ MORE +

What should you recommend for the placement of down-flow air conditioners?

A computer room with a raised floor has been designed with racks in a hot/cold aisle setup. What should you recommend for the placement of down-flow air conditioners?A . Air conditioners perpendicular to (at the end of the row of) the Cold-AisleB . Air conditioners perpendicular to (at the end...

March 24, 2025 No Comments READ MORE +

What is the main reason to install Earth Leakage protection?

What is the main reason to install Earth Leakage protection?A . Protection of ICT equipment against high-frequency noise currentsB . Protection of human livesC . Improvement of the data center grounding/earthing systemD . Protection against lightning strikesView AnswerAnswer: B Explanation: Earth Leakage Protection is primarily installed to protect human lives...

March 18, 2025 No Comments READ MORE +

What information is missing to perform the battery calculation?

Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS: • Rated power: 30 kVA • Rectifier input voltage: 400 V/3 phase • Rectifier input power factor: 0.8 • Battery rated voltage: 384 V • Number...

March 5, 2025 No Comments READ MORE +

What is a potential disadvantage of using a hypoxic-based fire suppression system as a fire extinguishing system?

What is a potential disadvantage of using a hypoxic-based fire suppression system as a fire extinguishing system?A . It can only be used in computer rooms which have sufficient air changes per hour.B . The gas containers need to be close to the hazard area.C . It can only be...

February 18, 2025 No Comments READ MORE +

Are new floor loading calculations required?

A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center. Are new floor loading calculations required?A . No, as long as the equipment is less than 700 kg/1,500 lbs it will be within the limits.B ....

February 16, 2025 No Comments READ MORE +

Do employers need to take precautions?

The noise levels in the data center are approximately 91 dB (A). Do employers need to take precautions?A . No, anything less than 100 dB (A) is acceptable.B . There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.C ....

February 15, 2025 No Comments READ MORE +

When are the wet bulb and dry bulb temperatures identical?

When are the wet bulb and dry bulb temperatures identical?A . When the dry bulb's temperature is at the lowest allowable temperature for IT equipment as per ASHRAEB . When the dry bulb's temperature is at the highest allowable temperature for IT equipment as per ASHRAEC . When the relative...

January 23, 2025 No Comments READ MORE +

B. To which feed will the output of the UPS be synchronized?

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B. To which feed will the output of the UPS be synchronized?A . The UPS will not synchronize to any of...