During which stage of the procurement cycle would you remove suppliers that do not add value, or could pose a risk to the buying organisation?
During which stage of the procurement cycle would you remove suppliers that do not add value, or could pose a risk to the buying organisation?
A . develop strategy
B . supplier selection
C . contract award
D . asset management
Answer: B
Explanation:
At supplier selection stage, unsuitable suppliers should be removed (those that do not add value or pose a risk). At develop strategy stage you’re not even looking at suppliers yet- you’re just deciding what you need. At contract award and asset management it’s too late. CIPS procurement cycle – Procurement Supply Cycle | CIPS
Latest L4M4 Dumps Valid Version with 120 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments