During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis.
During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis.
To avoid this situation and minimize impact on the project, the user should have been:
A . given the opportunity to review the user acceptance test scripts.
B . involved in the development and sign-off of the business requirements.
C . identified as a stakeholder as part of the stakeholder analysis.
D . interviewed to understand how the user’s work would be impacted.
Answer: D