During the design phase of a software development project, the PRIMARY responsibility of an IS auditor is to evaluate the:
During the design phase of a software development project, the PRIMARY responsibility of an IS auditor is to evaluate the:
A . Future compatibility of the application.
B. Proposed functionality of the application.
C. Controls incorporated into the system specifications.
D. Development methodology employed.
Answer: C