During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?
During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?
A . Risk rating
B . Warning signs
C . Cost of the project
D . Symptoms
Answer: C