During a Sprint Retrospective, for what is the Product Owner responsible?

During a Sprint Retrospective, for what is the Product Owner responsible?
A . Participating as a Scrum Team member.
B . Summarizing and reporting the discussions to the stakeholders that he/she represents in the Scrum Team.
C . Capturing requirements for the Product Backlog.
D . The Product Owner should not take part in Sprint Retrospectives.

Answer: A