During a DMO procedure with SUM, after which phase is the repository first available on the target database? Please choose the correct answer.

During a DMO procedure with SUM, after which phase is the repository first available on the target database? Please choose the correct answer.
A . Uptime migration (EU_CLONE_MIG_UT_RUN)
B . ParaUel distribution (PARDIST_SHD)
C . Downtime migration (EU_CLONE_MIG_DT_RUN)
D . Shadow repository creation (EU_IMPORT*)

Answer: A