Due to the earthquake, a company’s IT system went down at 16:00 on November 11 leading to a business halt. By 23:00 on the same day, the IT system resumed operation and the data at 12:00 of that day can be restored. Then what respectively are the RTO and the RPO?
A . RTO=4 hours, RPO=7 hours
B . RTO=7 hours, RPO=4 hours
C . RTO=2 hours, RPO=4 hours
D . RTO=7 hours, RPO=3 hours
Answer: B