Due to commitments to another project, an accountant fails to deliver an important report, what should the project manager nave referenced to avoid this?
A . Responsible, accountable, consult, and inform (RACI) matrix
B . Resource allocation plan
C . Resource calendar
D . Timesheets
Answer: C