A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
• Create a vendor resource and work cell for outsourced painting; add the vendor resource to the work cell.
• Create a production flow process activity using the painting work cell and the service item for picking.
• When the service is required, create a purchase order to the subcontracting vendor and add a line for the service item and the vendor price.
Does the solution meet the goal?
A . Yes
B . No
Answer: A
Explanation: