Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition.

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition.

What individual should respond to the risk with the preplanned risk response
A . Project sponsor
B . Risk owner
C . Diane
D . Subject matter expert

Answer: B