An administrator configures a lease policy with the following settings:
Maximum lease (days): 10
Maximum total lease (days): 30
Grace period (days): 5
If a user does not respond to any emails, after how many days will the deployment be
destroyed? (Choose the best answer.)
A . 15
B . 10
C . 35
D . 40
Answer: A
Explanation:
Reference: https://docs.vmware.com/en/vRealize-Automation/8.1/Using-and-Managing-Service-Broker/GUID-87B2B204-3B4F-458F-826E-82CE7246FDA4.html