What is a requirement for the vSAN Data-at-Rest Encryption?

What is a requirement for the vSAN Data-at-Rest Encryption?A . All-Flash or AII-NVMe VxRailB . VxRail with at least 3 nodesC . External Key Management ServerD . External customer provided vCenterView AnswerAnswer: C

July 29, 2022 No Comments READ MORE +

CORRECT TEXT

CORRECT TEXT A VxRail implementation engineer is validating the network environment with NVT. The proposed switch configuration is shown in the exhibit. The ToR Switch information file is available. Use the VxRail simulator to set up NVT for switch validation. Import the switch Information and tag the ports based on...

July 29, 2022 No Comments READ MORE +

Which settings must be used to ensure successful installation?

The VxRail Deployment Wizard is being used on a VxRail cluster with a customer-supplied VDS . Which settings must be used to ensure successful installation?A . Use the VxRail vCenter Server Upload a configuration file (JSON)B . Join an external vCenter Server Use the step-by-step methodC . Use the VxRail...

July 29, 2022 No Comments READ MORE +

What is the minimum number of VxRail nodes required for a vSAN storage policy with RAID-6 (Erasure Coding)?

What is the minimum number of VxRail nodes required for a vSAN storage policy with RAID-6 (Erasure Coding)?A . 4B . 5C . 6D . 7View AnswerAnswer: C

July 27, 2022 No Comments READ MORE +

What actions must be taken to retrieve the JSON file?

When preparing to generate an As-Built Configuration Report, it is determined that the VxRail Configuration JSON file was not saved from the Deployment Wizard . What actions must be taken to retrieve the JSON file?A . SSH to the VxRail Manager VM with the mystic user SU to root Go...

July 27, 2022 No Comments READ MORE +

Which two files are used to automate VxRail deployment and validate the network configuration?

Which two files are used to automate VxRail deployment and validate the network configuration?A . Appliance JSON file PEQ data fileB . VxRail Configuration Portal PEQ data fileC . VxRail Test Plan SPEQD . Appliance JSON file SPEQView AnswerAnswer: A

July 27, 2022 No Comments READ MORE +

What is a valid 2-node VxRail cluster configuration?

What is a valid 2-node VxRail cluster configuration?A . Series with 4x 25 GbE in a direct-connect configurationB . Series with 4x 10 GbE in a switch configurationC . Series with 4x 1 GbE in a direct-connect configurationD . Series with 2x 25 GbE in a switch configurationView AnswerAnswer: B

July 27, 2022 No Comments READ MORE +

What is the protocol for recording the results'?

A VxRail Test Plan has been completed What is the protocol for recording the results'?A . With the implementation team, complete and document each test, test date, and a screenshot of resultsB . In front of a customer, complete each test and document the test dateC . With the implementation...

July 27, 2022 No Comments READ MORE +

Which command is used to restart the Loudmouth process on an ESXi node?

Which command is used to restart the Loudmouth process on an ESXi node?A . /usr/IibAmiware/loudmouth/bin/loudmouthd restartB . systemcti restart loudmouthC . /etc/int.d/loudmouth restartD . systemcti restart vmware-loudmouthView AnswerAnswer: C

July 27, 2022 No Comments READ MORE +

Which command can be used from the VxRail Manager VM to restart the loudmouth daemon?

Which command can be used from the VxRail Manager VM to restart the loudmouth daemon?A . systemctl restart loudmouthB . /usr/lib/vmware/loudmouth/bin/loudmouthd restartC . /etc/init.d/loudmouth restartD . systemctl restart vmware-loudmouthView AnswerAnswer: D

July 27, 2022 No Comments READ MORE +