What files are used to validate the VxBlock components in VxBlock Central Core Vision VM during an RCM upgrade?
- A . system.cfg and vblock.xml
- B . system.json and vblock.xml
- C . vblock.xml and scr.cfg
- D . system.cfg and vblock.json
Who is an optional resource during an RCM upgrade escalation?
- A . Customer Advocate
- B . Program Manager
- C . Account Team
- D . Assessment Lead
You are deploying a VxBlock system with Cisco ACI.
What is a consideration?
- A . Leaf switches use 40 GbE vPC peer links
- B . Fabric load balancing is achieved using VXLAN
- C . A minimum of four uplinks per leaf switch is recommended
- D . Leaf switches connect to spines using 40 GbE links
In which phase of the RCM Upgrade process does the warm hand-off between the Assessment team and the RCM Upgrade Team occur?
- A . Closure and Lessons Learned
- B . Executing and Controlling
- C . Planning
- D . Initiation
How many business days is the duration of a Knowledge Transfer session?
- A . 1
- B . 2
- C . 3
- D . 4
A Cisco UCS 5108 chassis contains five blades.
How many additional full-width blades can be added?
- A . 0
- B . 1
- C . 2
- D . 3
Based on the RCM Upgrade RACI, which role owns the process, and which role provides input to the process?
- A . Owner: Assessment Lead
Provides input: Assessment Team - B . Owner: Assessment Lead
Provides input: Project Manager - C . Owner: Program Manager
Provides input: Project Manager - D . Owner: Project Manager
Provides input: Assessment Lead
Where can VxBlock expansion documents be found?
- A . SolVe, support.vce.com
- B . FlexNet, CPSD Technical Resource Center
- C . SolVe, Nirvana RCM DB
- D . CPSD Technical Resource Center, SolVe
Which data layout technique is used by Isilon OneFS to provide N-way failure and tolerance?
- A . Forward Error Correction (FEC) only
- B . File Striping only
- C . Forward Error Correction (FEC) and File Striping with Mirroring
- D . Mirroring only
During which phase of the RCM Upgrade Timeline should the Pre-Upgrade Questionnaire be completed and reviewed by the team?
- A . Remediation
- B . Assessment
- C . Kickoff
- D . Initialization