A technician needs to configure the Lifecycle Controller network settings with a static IP address. A limited number of static IP addresses are available for use.
Which previously assigned IP address can also be used for the Lifecycle Controller?
- A . The host operating system’s IP address
- B . The iDRAC IP address
- C . The IP address of a different server on the network
- D . The default gateway IP address
Which memory operation modes are supported for a Dell PowerEdge R660?
- A . Optimizer and Persistent Memory
- B . Optimizer and Dell Default Resilient
- C . Optimizer and Mirror
- D . Dell Default Resilient and Mirror
A technician has a 13G system that is giving NO video to a crash cart connected to the front VGA port. The LCD is NOT reporting any errors.
The system reports ‘CPU Resetting’ messages sporadically in the lifecycle log. The iDRAC runs an Express license. The technician needs to most efficiently determine if the system is completing POST despite the video issue.
Which two steps should the technician take to perform this task? (Choose two.)
- A . Reduce to minimum to post
- B . Launch the iDRAC virtual console
- C . Connect to rear VGA port
- D . Hold the system identification button for 6 seconds
A Dell EMC PowerEdge 13G server is being controlled through a secure port by iDRAC8.
What login connection options are available on server using a secure port?
- A . DRM only
- B . RACADM CLI and DRM
- C . Web GUI and RACADM CLI
- D . Web GUI and SSH
A technician needs to analyze a server that is using more power than expected. The server is part of a cluster that runs jobs between 8 AM and 5 PM. The cluster is not used at other times of the day. The server runs an unsupported OS. Performance while jobs are running is a key consideration.
Which option should the technician choose from within System Profile Settings within System Setup to address this issue?
- A . Dense Configuration
- B . Performance Per Watt (DAPC)
- C . Performance
- D . Performance Per Watt (OS)
Case Study 1
A company has several independent business units that operate globally. The company has consolidated its IT infrastructure services and operations. Common infrastructural services which include IPAM, DNS, NTP, DHCP, and SMTP have been consolidated.
The company has complimented its infrastructure development by investing in Dell EMC Isilon clusters to host its user’s home and group directories and for compliance archival purposes required by individual business units. The IT operations are located in India and the United States with its primary data center facilities co-located between New York and Texas.
The company has a total of 60 AD forests:
– 1 main domain
– 55 domains have one-way trust relationships with the main domain
– An additional 4 domains do not have any trust relationship with no future plans of establishing trust relationships with the other domains.
Users of different AD domains use different FQDN to access their corresponding file services. Additionally, the company does not plan to consolidate the AD domains and each domain uses a different IP subnet.
The users of the domains with no trust relationships have a compliance archival requirement. The company wants to all data to be replicated between New York and Texas.
How many tenant Access zones will be required?
- A . 1
- B . 55
- C . 59
- D . 60
A technician needs to update the iDRAC license on a PowerEdge R740 server from Express to Enterprise.
The server has the following components:
– 2x CPUs
– 384 GB RAM
– 6x 1 TB drives
– 1x PSU
The server is powered down but connected to active AC. The user wants it to stay powered down and not connect to any networks. No errors are presently displayed.
How can the technician upgrade the license?
- A . The license cannot be upgraded because the user will not allow the server to be powered on
- B . The license cannot be upgraded on a single PSU system
- C . Power on the server then connect to the iDRAC and upgrade iDRAC license before powering the server down
- D . Connect to the iDRAC GUI and upgrade the iDRAC license while the server is powered down.
Where is the data stored to allow Easy Restore to successfully complete a system board replacement?
- A . NAND Flash module on the disk drive mid plane
- B . IDSDM SD card
- C . vFlash SD card
- D . Serial Flash storage in the server’s front panel
Beginning with which generation Dell EMC PowerEdge server is the NDC available?
- A . 11G
- B . 12G
- C . 13G
- D . 14G
A user installed OME on a PowerEdge R640 server. OME has discovered and is currently monitoring another 30 remote PowerEdge 14G servers.
Each server has the following configuration:
– 2x CPUs
– 384 GB RAM
– 6x 1TB drives in a RAID 6 virtual disk
– No hot spare drive
– PERC
– vFlash
– iDRAC9 Express license
At 9 PM on Monday evening, one of the remote servers has a disk failure but stays operational. The administrator monitoring OME does not find out about the issue until 5 PM in the following Friday. They place a support call to investigate why OME was not informed about the disk failure before then.
What is the reason for this issue not being reported to OME?
- A . Remote servers are not configured with OME as the trap destination address. OME discovered the issue during a routing status check which is configured to run at 5 PM every Friday.
- B . OME only updates its alert database at 5 PM every Friday.
- C . Remote servers are not configured with OME as the trap destination address. OME was informed of the issue when remote servers sent alerts at 5 PM Friday.
- D . Remote servers need to have the iDRAC Enterprise license installed to be able to send alerts.