Delivery is expected in 6 Sprints. Will this project deliver the anticipated impact?
Team A has a velocity of 50 with a Product Backlog of 140 points ordered by business value as perceived by stakeholders.
Delivery is expected in 6 Sprints. Will this project deliver the anticipated impact? (choose the best answer)
A . We do not know
B. Yes
C. No
Answer: A
Explanation:
None of the information provided gives you any insight into the value the product delivers.