Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
A . Enterprise environmental factors
B. Work performance reports
C. Organizational process assets
D. Context diagrams
Answer: A
Latest CAPM Dumps Valid Version with 1089 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments