Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
- A . Smoke testing
- B . Regression testing
- C . Unit testing
- D . User acceptance testing
To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely.
Which a following technique is the project manager utilizing?
- A . Process moving
- B . Brainstorming
- C . Interview
- D . Focus group
Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?
- A . Telephone
- B . Videoconference
- C . Face-to-face
- D . Email
Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect.
Which of the following actions should the project manager take NEXT?
- A . Escalate directly to the project sponsor
- B . Push the kickoff meeting out by one week
- C . Proceed with the kickoff as planned
- D . Identity replacements for project stakeholders
A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations.
Which of the following tools should the project manager use to validate the functionality?
- A . Project status report
- B . Requirements Traceability Matrix
- C . Detect log
- D . Signed project charter
- E . Work breakdown structure
A PM is working on a strategy to store records.
Which of the following dements must be included in this plan? (Select TWO)
- A . Data management
- B . Issue management
- C . Work breakdown structure
- D . Document management
- E . Communication management
- F . Risk management
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users’ desks. The requirements do not specify where to place the items, just what is needed in each space.
Which of the following should the project manager do to resolve the conflict?
- A . Send out a survey to the potential end users to gather information about the best functional setup for work productivity.
- B . Provide clear instructions based on personal preference and aesthetics for setup of the work areas.
- C . Explain to team members that the placement of the items is not too important, as long as everything is connected and working.
- D . Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.
Given the following velocity chart:
Which of the following updates on the project status should the Scrum master provide to the senior management team?
- A . The project utilized all of its available reserve.
- B . The project has scope creep.
- C . The project deviated from the critical path.
- D . The project is trending ahead of schedule.
A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources.
Which of the following risk responses does this demonstrate?
- A . Avoid
- B . Transfer
- C . Accept
- D . Share
During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation.
Which of the following was applied?
- A . Awareness of the local environment
- B . Awareness of the brand value
- C . Awareness of the resource constraints
- D . Awareness of the company’s mission