A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?
- A . Planning
- B . Initiating
- C . Controlling
- D . Executing
A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project.
Which of the following should the project manager do next?
- A . Buy a replacement for the faulty equipment.
- B . Get the maintenance team to resolve the issue.
- C . Escalate the issue to the project sponsor.
- D . Rate the severity of the impact the issue has on the project.
A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time.
Which of the following should the project manager do next?
- A . Request a change control ticket.
- B . Review the schedule plan.
- C . Refine the project documentation.
- D . Revise the communication plan.
During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase.
Which of the following documents is the best source for the PM to use to confirm this assertion?
- A . Issue log
- B . Scope statement
- C . Risk report
- D . Change log
Which of the following activities are important parts of the closing phase? (Select two).
- A . Releasing resources
- B . Locking risks
- C . Updating stakeholder register
- D . Closing contracts
- E . Completing the work breakdown structure
- F . Negotiating the next project
A project manager has been very diligent in maintaining the version control for the documentation of requirements.
Which of the following tools is the project manager using?
- A . Multiauthoring software
- B . Word processor
- C . Real-time polling
- D . Conferencing platforms
A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions.
Which of the following communication methods should the project manager use?
- A . Synchronous
- B . Informal
- C . Asynchronous
- D . Formal
Which of the following is a consideration when determining a project’s ESG factors?
- A . Project management methodology
- B . IT infrastructure security
- C . Proper accounting practices
- D . Corporate values compliance
A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project.
Which of the following is the most likely cause of this situation?
- A . The retrospective session feedback was not communicated properly.
- B . The project resources were released ahead of time.
- C . The documentation was not archived as per the PMO standards.
- D . The validation of deliverables is running behind schedule.
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed.
Which of the following actions should the project manager MOST likely perform?
- A . Work with the project scheduler to update the project timeline.
- B . Communicate to the stakeholders about the updated timeline.
- C . Ask the development team to fast-track upcoming activities.
- D . Add two resources so the critical activities will finish on time.