A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality.
Which of the following should the project manager do in response to the request?
- A . Decline because it is not included in the project scope.
- B . Assess the impact of the request and create a change request
- C . Create new functional and non-functional requirements for mobile devices.
- D . Revise the baseline of the project plan by adding the new requirements.
A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings.
Which of the following types of communication is the sponsor using?
- A . Informal communication
- B . Formal communication
- C . Synchronous communication
- D . Asynchronous communication
A project team gathers weekly to review its progress.
Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
- A . Status report
- B . Project plan
- C . Change log
- D . Meeting minutes
A project manager and team are currently in the planning phase of a project.
Which of the following should the team do during this phase?
- A . Identify and assess stakeholders.
- B . Hold daily status meetings.
- C . Remove access and plan the project sign-off.
- D . Review assumptions and constraints for input to the risk register.
Which of the following items must be protected as Pll? (Select TWO).
- A . Job title
- B . Home address
- C . Work phone number
- D . Time zone
- E . Date of birth
- F . Blood type
An opportunity emerged in the middle of a project life cycle.
Which of the following is the BEST action for the project manager to take?
- A . Exploit the risk.
- B . Accept the risk.
- C . Avoid the risk.
- D . Transfer the risk.
After new capabilities were deployed in a system, issues with preexisting capabilities were reported.
Which of the following testing cycles should be used to prevent this issue?
- A . Performance testing
- B . User acceptance testing
- C . Stress testing
- D . Unit testing
A contractor attended a project meeting that was exclusively for company employees.
Which of the following actions should the PM take?
- A . Escalate to vendor management.
- B . Consult the request for proposal.
- C . Review the meeting cadence.
- D . Reinforce the rules of engagement.
A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution.
Which of the following actions should the project manager most likely take?
- A . Ask a developer to create a change request.
- B . Do nothing because recommendation is scope creep.
- C . Ask a developer to implement the recommendation.
- D . Communicate the change status.
Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product.
Which of the following documents should the project manager expedite first?
- A . RFI
- B . RFP
- C . RFQ
- D . RFB