CompTIA PK0-005 CompTIA Project+Certification Online Training
CompTIA PK0-005 Online Training
The questions for PK0-005 were last updated at Jan 01,2025.
- Exam Code: PK0-005
- Exam Name: CompTIA Project+Certification
- Certification Provider: CompTIA
- Latest update: Jan 01,2025
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members.
Which of the following describes this organizational structure?
- A . Flat
- B . Projectized
- C . Weak matrix
- D . Functional
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication.
The project manager should update the stakeholder register with:
- A . the preferred sponsor’s communication channel.
- B . the preferred project manager’s communication channel.
- C . the preferred reported communication channel.
- D . email communication as the preferred communication channel.
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date.
Which of the following should the project manager do first?
- A . Escalate the change to the CCB.
- B . Review the requested change.
- C . Document the change recommendations.
- D . Validate the implementation of the requested change.
Which of the following is a reason to use a SOW on a project?
- A . To find out the contact information for the vendors
- B . To review the list of stakeholders
- C . To ensure the team stays within the scope of the contract
- D . To give explicit instruction on how to execute the work
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects.
Which of the following tools should the project team use to find the cause?
- A . Kanban board
- B . Pareto chart
- C . Ishikawa diagram
- D . Decision tree
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users’ desks. The requirements do not specify where to place the items, just what is needed in each space.
Which of the following should the project manager do to resolve the conflict?
- A . Send out a survey to the potential end users to gather information about the best functional setup for work productivity.
- B . Provide clear instructions based on personal preference and aesthetics for setup of the work areas.
- C . Explain to team members that the placement of the items is not too important, as long as everything is connected and working.
- D . Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.
During the project initiation phase, a project team has been identified.
Which of the following is the NEXT step for the project manager?
- A . Determine budget constraints.
- B . Validate the business case.
- C . Update the project charter.
- D . Create a project schedule
A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources.
Which of the following risk responses does this demonstrate?
- A . Avoid
- B . Transfer
- C . Accept
- D . Share
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan.
Upon further investigation, the document contains:
* Purpose
* Scope of work
* Location of work
* Period of performance
* Deliverables schedule
* Applicable standards
* Acceptance criteria
* Special requirements
* Payment schedule
Which of the following documents did the client provide to the project manager?
- A . RFP
- B . WBS
- C . SLA
- D . SOW
Government projects require that personnel submit to background screenings for certain clearance requirements.
Which of the following best describes this process?
- A . Data security
- B . Operational security
- C . Physical security
- D . Digital security