A project team was instructed to refurbish old desktops.
The following provides the details of the issues observed:
Which of the following issues should be addressed FIRST?
- A . Replace missing peripherals because this process can be easy and less costly.
- B . An old operating system issue has the most amount of occurrences.
- C . Damage to the monitor has the highest percentage.
- D . Address each issue as discovered to avoid rework.
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP.
Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
- A . Milestone chart
- B . Work breakdown structure
- C . Project charter
- D . Detailed scope statement
In a functional organization, a project has been completed successfully.
Which of the following actions would the project manager MOST likely perform?
- A . Assemble a new project with existing resources.
- B . Obtain the final report from release management.
- C . Notify the functional manager that resources are released.
- D . Allocate resources in a different project
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance.
Which of the following should the project manager put in place before work begins?
- A . Time and materials contract
- B . Master service agreement
- C . Fixed-price contract
- D . Statement of work
- E . Cost-plus agreement
Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?
- A . Assign action items to attendees.
- B . Distribute an agenda.
- C . Email the minutes from the previous meeting.
- D . Schedule a convenient time.
While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project.
Which of the following should the PM do FIRST?
- A . Escalate the finding to the change control board.
- B . Add a risk to the risk register for validation.
- C . Consult the RACI matrix to identify ownership of the risk.
- D . Have a meeting with the project sponsor and main stakeholders.
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product.
Which of the following charts would BEST prioritize which defects to address?
- A . Pareto
- B . Run
- C . Control
- D . Histogram
Which of the following activities would a project manager perform during the closing phase? (Select THREE).
- A . Lessons learned
- B . Risk analysis
- C . Removing resources
- D . Acquiring resources
- E . Statement of work sign-off
- F . Stakeholder analysis
- G . Removing access
Which of the following is a quality assurance tool?
- A . Defining project goals
- B . Identifying the root cause analysis
- C . Assessing employee efficiency
- D . Assessing skill gaps
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing.
Which of the following considerations is impacting the rest of the team?
- A . Quality assurance
- B . Organizational branding restrictions
- C . State privacy acts
- D . Country legal regulations