The questions for PK0-005 were last updated at Dec 30,2024.
- Exam Code: PK0-005
- Exam Name: CompTIA Project+Certification
- Certification Provider: CompTIA
- Latest update: Dec 30,2024
A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII.
Which of the following is the best approach for the project manager to keep the information confidential?
- A . Encryption
- B . Multifactor authentication
- C . Quality assurance
- D . Password protection
A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted.
Which of the following actions should the project manager take?
- A . List both positively and negatively impacted stakeholders.
- B . Update the communication plan with the new findings.
- C . List the negatively impacted stakeholders only.
- D . List the positively impacted stakeholders only.
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project.
Which of the following activities still needs to be performed to complete the schedule?
- A . Allocate resources.
- B . Determine the project budget
- C . Develop a communication plan.
- D . Establish baselines.
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system.
Which of the following was the cause of this situation?
- A . The ticket system provided access by default without any approval.
- B . The project manager did not perform proper project planning.
- C . The system is lacking proper access controls.
- D . Sensitive data was incorrectly classified during the audit process.
A PM is working on the preliminary scope statement and identifies that this project has the
same approach as another project that was completed last year.
Which of the following actions would the PM most likely perform?
- A . Call the previous PM for advice on risks and issues.
- B . Ask the project sponsor to provide previous final project report results.
- C . Complete the project charter using the other PM’s subject matter expertise.
- D . Use existing artifacts and accommodate based on the current project success criteria.
Which of the following pieces of data are examples of Pll?
- A . Medical record and test result values
- B . IP address and email address
- C . Name and year of birth
- D . X-ray and blood type
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
- A . Strong projectized organization
- B . Medium risk
- C . Lack of resources
- D . Multiple undefined tasks
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
- A . Implement the change.
- B . Approve the test plan.
- C . Notify customers.
- D . Develop a rollback plan.
Which of the following best describes a manufacturer’s obligation to repair or change, without extra costs, any part of a product that is not functioning?
- A . Service-level agreement
- B . Functional testing
- C . Warranty period
- D . Audit
After a migration was completed and a financial system was deployed, users have been unable to issue payment orders.
Which of the following should be implemented?
- A . Rollback plan
- B . Release plan
- C . Deployment plan
- D . Contingency plan