The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.
To alter the pace of the project, which of the following should the project manager do FIRST?
- A . Give approval for the change requested by the project sponsor.
- B . Deny the request from the project sponsor.
- C . Document the change request from the project sponsor.
- D . Ask the project sponsor to change the request.
Which of the following is a schedule that illustrates the duration of an activity?
- A . Process diagram
- B . Ishikawa diagram
- C . Gantt chart
- D . Pareto chart
C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168
Team members have reported that meetings are poorly attended and unproductive.
Which of the following steps can the project manager take to make the meetings more productive?
- A . Discontinue the meetings with the poorest attendance.
- B . Decrease the length of the meetings.
- C . Distribute an agenda before each meeting.
- D . Document team member attendance and report it to management.
C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326
Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.
The project manager should:
- A . follow the change process flow and notify the legal department after the change is implemented.
- B . extend a formal invitation to the legal department representative to join the CCB.
- C . hold a separate meeting with the legal department representative and ask for approval.
- D . notify the legal department representative in the event of an upcoming audit.
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294
A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.
Which of the following is the MOST likely reason?
- A . Established communication plan
- B . Scope creep
- C . Resource constraints
- D . Iterative approach
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133
In which of the following organizational structures would a project manager have the MOST authority?
- A . Projectized
- B . Strong matrix
- C . Balanced matrix
- D . Functional
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 57
A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility.
Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?
- A . Email
- B . Social media
- C . Text messaging
- D . Face-to-face
C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.
The project manager is concerned that the requests will lead to:
- A . quality control issues.
- B . additional risks.
- C . scope creep.
- D . time constraints.
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?
- A . Project charter
- B . Project management plan
- C . Project statement of work
- D . Project schedule
C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299
A project manager has noticed poor attendance as status meetings.
Which of the following strategies should the project manager use to improve attendance? (Choose two.)
- A . Provide an agenda before the status meeting.
- B . Adhere to an agenda and scheduled time.
- C . Add non-project-related items to the agenda.
- D . Add and discuss new agenda items throughout the meeting.
- E . Discard the action items at the conclusion of the meeting.