The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?
- A . The project manager should identify and document the reasons for the additional resources in a change request.
- B . The project manager should hire additional resources temporarily to complete the project.
- C . The project manager should terminate the project until additional resources are added to the project.
- D . The project manager should ask the project team members to take on more tasks to complete the project on time.
An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?
- A . PMO
- B . Project sponsor
- C . Project coordinator
- D . HR
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82
When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?
- A . Issue log
- B . Risk management plan
- C . Communications plan
- D . Risk register
- E . Status report
A milestone task on the critical path has been completed.
Which of the following should the project manager notify?
- A . Owner of predecessor task
- B . Project team
- C . Project sponsor
- D . Project steering committee
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.
Which of the following actions should the project manager take?
- A . Alert the project sponsor of the situation.
- B . Contact the customer and request more funding.
- C . Announce the project will end early due to lack of funds.
- D . Attempt to save money in downstream activities.
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 233
Which of the following is the primary purpose of an MOA or an MOU?
- A . State expectations of all signatory parties to reduce potential misunderstandings.
- B . Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.
- C . Enumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program.
- D . Provide transparency to competitors regarding all signatory parties.
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized?
- A . Smoothing
- B . Forcing
- C . Compromising
- D . Avoiding
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?
- A . Execution
- B . Kickoff
- C . Closure
- D . Planning
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112
A project manager is working on the project charter.
Which of the following phases does this describe?
- A . Initiation
- B . Planning
- C . Execution
- D . Closing
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107
A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT?
- A . Update the project management plan.
- B . Issue a change request.
- C . Revise the project charter.
- D . Evaluate the impact to the baseline.