Which of the following is a key aspect of the Agile project management methodology?
- A . Test-driven
- B . Daily standup meetings
- C . Short project durations
- D . Defined list of requirements
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?
- A . Assess the risk register’s new items.
- B . Review the task start and finish dates.
- C . Obtain additional resources.
- D . Analyze the assigned hours.
A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements.
Which of the following actions would be BEST for the project manager to take?
- A . Ask the client to provide additional language resources to the team.
- B . Purchase a language translation program.
- C . Hire a translator to help the key team member
- D . Ask the client to provide requirements in the native language of the team.
After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?
- A . Use milestones identified in the project charter.
- B . Use data based on past knowledge.
- C . Hold a full team workshop to review the complete WBS.
- D . Collaborate with other project managers.
A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?
- A . Outsourcing
- B . Business acquisition
- C . Business process change
- D . Internal reorganization
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297
A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.
Which of the following constraints are MOST likely to be affected? (Choose two.)
- A . Quality because the existing system is now outside the threshold.
- B . Requirements because this is a change to initial scope.
- C . Cost because replacing the system incurs additional expense.
- D . Schedule because this was an unscheduled task and will impact the timeline.
- E . Stakeholders because they will need to understand the modification and provide buy-in.
C,D
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293
Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
- A . SCRUM retrospective
- B . Kickoff meeting
- C . Budget baseline
- D . Risk review
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306
The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?
- A . Balanced score card
- B . WBS
- C . Post-project evaluation
- D . PERT
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 332
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
- A . forcing.
- B . avoiding.
- C . smoothing.
- D . compromising.
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
- A . EAC
- B . BAC
- C . CPI
- D . ETC
C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231