A project manager has contracted a third-party vendor to achieve milestones.
Which of the following risk strategies is the project manager applying?
- A . Transfer
- B . Accept
- C . Avoid
- D . Mitigate
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238
A company is hired to perform some of another organization’s work.
Which of the following types of organizational change is described?
- A . Outsourcing
- B . Business process change
- C . Shared resources
- D . Split
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
- A . Additional resources
- B . A gate review
- C . A risk register update
- D . A performance audit
C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 272