Which of the following events would MOST likely trigger communications to the largest audience for a given organization?
- A . Business continuity response
- B . Quality audit
- C . Replacement of a subcontractor
- D . Completion of a task
A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 273
If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?
- A . The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
- B . The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
- C . The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
- D . The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?
- A . Compromising
- B . Smoothing
- C . Withdrawing
- D . Accepting
C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:
- A . an RFP.
- B . an NDA.
- C . an SLA.
- D . an MOU.
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 302
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
- A . Project manager and project scheduler
- B . Project coordinator and project sponsor
- C . Project champion and project scheduler
- D . Project stakeholders and project team
D
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?
- A . Submit a new change request.
- B . Initiate the regression plan.
- C . Add remediation to the schedule.
- D . Accept the new power output.
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294
A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?
- A . Tell the senior manager the estimation is not available yet.
- B . Use the budget from a similar project to generate estimates.
- C . Ask a SME for an opinion and propose an estimate.
- D . Gather the team to immediately generate estimates.
B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 164
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)
- A . Scope management plan
- B . Configuration management plan
- C . Network diagram
- D . Project schedule
- E . Project plan
C,D
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 171
A company has dictated project scope changes but has stated that the original budget still applies.
Which of the following will MOST likely be impacted by the changes?
- A . Quality
- B . Regulations
- C . Schedule
- D . project team
C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133
A project manager was directed to complete a project sooner than previously planned.
Which of the following is the MOST cost-effective step to take to ensure the project’s success?
- A . Reduce the scope
- B . Increase the budget
- C . Decrease staff
- D . Update the WBS
D
Explanation:
References: https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+sooner+-+update+WBS&source=bl&ots=O650UKpUEK&sig=mlexbBmFJKkAuXuftqO2YjLLOgo&hl=en&sa=X&ved=0ahUKEwi8uJXIj_DXAhUKuRQKHW3fDKAQ6AEIMTAC#v=onepage&q=complete%20a%20project%20sooner%20-%20update%20WBS&f=false