Company A sells a product for $100. The total unit variable costs are $60. Fixed costs as in its ac-count are $20,000.
How many products does the company have to sell to achieve break-even point?
- A . 600
- B . 550
- C . 400
- D . 500
Company A sells a product for $100. The total unit variable costs are $60. Fixed costs as in its ac-count are $20,000.
How many products does the company have to sell to achieve break-even point?
- A . 600
- B . 550
- C . 400
- D . 500
Company A sells a product for $100. The total unit variable costs are $60. Fixed costs as in its ac-count are $20,000.
How many products does the company have to sell to achieve break-even point?
- A . 600
- B . 550
- C . 400
- D . 500
Company A sells a product for $100. The total unit variable costs are $60. Fixed costs as in its ac-count are $20,000.
How many products does the company have to sell to achieve break-even point?
- A . 600
- B . 550
- C . 400
- D . 500
Company A sells a product for $100. The total unit variable costs are $60. Fixed costs as in its ac-count are $20,000.
How many products does the company have to sell to achieve break-even point?
- A . 600
- B . 550
- C . 400
- D . 500
The substitute fits organization’s strategy
- A . 1 and 4 only
- B . 3 and 4 only
- C . 1 and 2 only
- D . 2 and 4 only
GSC Ltd is a manufacturer of car parts. To accommodate growing demands of electric cars, the company is developing a new component which requires different type of steel. The project team estimates that the component will be ready for production in 1.5 years. Until then, they need to keep the production busy.
After checking the inventory records, the production team sees that the company has 3 months of stock. The lead time for each batch is two months.
Which of the following should be a priority action of the company?
- A . Create new specification to new supplier
- B . Standardise the specification
- C . Create new specification to current supplier
- D . Make a call-off order to current supplier
GSC Ltd is a manufacturer of car parts. To accommodate growing demands of electric cars, the company is developing a new component which requires different type of steel. The project team estimates that the component will be ready for production in 1.5 years. Until then, they need to keep the production busy.
After checking the inventory records, the production team sees that the company has 3 months of stock. The lead time for each batch is two months.
Which of the following should be a priority action of the company?
- A . Create new specification to new supplier
- B . Standardise the specification
- C . Create new specification to current supplier
- D . Make a call-off order to current supplier