A process contains only 4 stages Study the following process flow:
The data Item Result’ is a number data item with an initial value of 2.
The calculation stage is configured as follows:
Following the execution of the Perform Calculation stage, which of the following is true?
- A . The data item Result will contain 3
- B . The data item Result will contain 5
- C . The process will throw an exception
- D . None of these statements are correct
A process contains only 4 stages. Study the following process flow.
The data item New Date is a date data item with no initial value.
The calculation stage is configured as follows:
What will happen when you execute the Create Date stage?
- A . 5 days will be added to today’s date and the result stored in the New Date data item.
- B . 1 month will be added to today’s date and the result stored in the New Date data item.
- C . 1 week will be added to today’s date and the result stored in the New Date data item.
- D . The process will throw an exception as the New Date data item is null.
Consider the following process flow:
Decision “A” properties are:
Decision “B” properties are:
Decision “C” properties are:
What will happen when the process runs?
- A . The flow will pass through calculation stage "A"
- B . The flow will pass through calculation stage "B"
- C . The flow will pass through calculation stage "C"
- D . An exception will be thrown
The following Calculation Stage uses the Today function to get the current date as a date value and place it in a data item entitled "Today".
Which of the following statements is correct?
- A . If the data item "Today" is configured with a Data Type of Text, an exception will be thrown on execution of the calculation stage
- B . If the data item "Today" is configured with a Data Type of Date, an exception will be thrown on execution of the calculation stage
- C . If the data item "Today" is configured with a Data Type of DateTime, an exception will be thrown
on execution of the calculation stage - D . None of these statements are correct
Study at the following diagram which is an extract from a sub-page of a process being tested in
Process Studio:
There are no breakpoints in the "Access Customer Account" subpage however there is an error.
What will happen if you choose to step out (SHIFT+ F11) when debugging the process?
- A . The process will work all stages in the "Access Customer Account page until the error is thrown and then focus would move to the breakpoint at "Get Customer Details" stage.
- B . The process will work all stages in the ‘Access Customer Account1 page until the error is thrown and then focus would move to the "Recover 1 stage
- C . The process will work all stages in the "Access Customer Account’ page until the error is thrown and then focus would move to the stage containing the error on the "Access Customer Account" page,
- D . The process will work all stages in the "Access Customer Account" page until the error is thrown and then focus would move to the "Exception 1 stage.
Study at the following diagram which is an extract from a process being tested in Process Studio:
There are no breakpoints in the "Access Customer Account" subpage however there is an error.
What will happen if you choose to step over (F10) when debugging the process?
- A . The process will work all stages in the; Access Customer Account" page until the error is thrown and then focus will move to the "Get Customer Details" stage.
- B . The process will work all stages in the "Access Customer Account" page until the error is thrown and then focus will move to the "Recover 1 stage.
- C . The process would will all stages in the "Access Customer Account’ page until the error is thrown and then focus will move to the stage containing the error on the ”Access Customer Account" page.
- D . The process will work all stages in the ‘Access Customer Account" page until the error is thrown and then focus would move to the appropriate recover stage on the ‘Access Customer Account" page.
Which of the following Stages can be found Process Studio but NOT Object studio?
- A . Option A
- B . Option B
- C . Option C
- D . Option D
When mapping the Training application the User field has been spied, but on highlight the following situation is encountered:
Which of the following attributes would you use to help obtain a unique match?
- A . Ordinal
- B . parent Windows Text
- C . Height
- D . Control ID
Which of the following about an object’s run mode is true?
- A . A run mode of background will enable the business object to run at the same time as other foreground business objects
- B . A run mode of background will enable the business object to run at the time a other background, foreground and exclusive business objects
- C . A run mode of exclusive cannot at the same time as any other business object
- D . The run mode of a business object has no influence on how many business objects can be run at the same time
How can an environment variable value be updated? (select all that apply)
- A . By using the Internal – Environment Variables business object
- B . By changing the Blue Prism Server configuration
- C . By updating the value in Control Room
- D . By updating the value in Credential Manager.