Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?
Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?
A . Verify the equipment controls are in the proper operating position.
B . Train workers to perform the LOTO process.
C . Apply appropriate tags both locally and remotely.
D . Confirm the device is de-energized by proving it will not run when started.
E . Confirm all unnecessary items have been removed from the area.
Answer: C