Based on this information, what should the project manager conclude about project performance’?
A project manager has received an updated earned value analysis report.
The following are the key findings from the report
• Budget at completion = USS1 million
• Earned value = US$0 7 million
• Actual cost = US$0 75 million
• Cost performance index = 0 933
Based on this information, what should the project manager conclude about project performance’?
A . The project will be completed exactly as planned
B . The project will be easier to complete than planned
C . The project will be difficult to complete as planned.
D . The project will not be completed as planned
Answer: D