Based on this information, what should the project manager conclude about project performance’?

A project manager has received an updated earned value analysis report.

The following are the key findings from the report

• Budget at completion = USS1 million

• Earned value = US$0 7 million

• Actual cost = US$0 75 million

• Cost performance index = 0 933

Based on this information, what should the project manager conclude about project performance’?
A . The project will be completed exactly as planned
B . The project will be easier to complete than planned
C . The project will be difficult to complete as planned.
D . The project will not be completed as planned

Answer: D