A solution architect has been tasked with designing a new environment for a company’s growing needs, and has obtained this information:
• Uptime is critical during regular business hours when 95% of the transactions occur. Application uptime must be 99.9% during those hours.
• In a true Disaster, the business can withstand a day of data loss and half a day of downtime.
• The company is one year into a 5-year contact with the co-lo data center.
• The building that is currently occupied no hanger has any floor space available, but the company has 3 empty racks of space. The co-lo can provide up to 11KVA of power per rack.
• There are current contacts with Dell to provide servers and with Cisco to provide the network components.
• The network team has standardized on an end-to-end 10Gb network.
Based on this information, what are two requirements for the new design? (Choose two.)
A . RTO of 24 hours.
B . RTO of 12 hours.
C . The application must be available 99.9% during business hours.
D . 11KVA of power is available per rack.
Answer: BC