Based on this information, the CPI reflects which of the following about the project?

A project manager is creating the monthly report for top management.

The project manager has collected the information below:

AC = 100

PV = 80

EV = 120

Based on this information, the CPI reflects which of the following about the project?
A . It is under budget.
B . It is over budget.
C . It is ahead of schedule.
D . It is behind schedule.

Answer: A

Explanation:

“The cost performance index (CPI)

is calculated this way:

CPI = EV / AC”

Excerpt From: Kim Heldman. “CompTIA Project+ Study Guide.” iBooks.