Based on this information, the CPI reflects which of the following about the project?
A project manager is creating the monthly report for top management.
The project manager has collected the information below:
AC = 100
PV = 80
EV = 120
Based on this information, the CPI reflects which of the following about the project?
A . It is under budget.
B . It is over budget.
C . It is ahead of schedule.
D . It is behind schedule.
Answer: A
Explanation:
Explanation
“The cost performance index (CPI) is calculated this way:
CPI = EV / AC”
Excerpt From: Kim Heldman. “CompTIA Project+ Study Guide.” iBooks.