Based on the scenario above, what is the calculated event rate per 24 hours?

A company has 1,000 Cisco switches in their environment that send approximately 5,000 traps each to the Netcool system in a 24 hour period. In addition to this, they have 5,000 servers and workstations; each sending approximately 100 syslog messages to IBM Tivoli Netcool/OMNIbus in the same time period.

Based on the scenario above, what is the calculated event rate per 24 hours?
A . 5,500,000 events
B . 2t500,000 events
C . 1,000,000 events
D . 6,000,000 events

Answer: D