Based on the scenario above, what is the calculated event rate per 24 hours?
A company has 1,000 Cisco switches in their environment that send approximately 5,000 traps each to the Netcool system in a 24 hour period. In addition to this, they have 5,000 servers and workstations; each sending approximately 100 syslog messages to IBM Tivoli Netcool/OMNIbus in the same time period.
Based on the scenario above, what is the calculated event rate per 24 hours?
A . 5,500,000 events
B . 2t500,000 events
C . 1,000,000 events
D . 6,000,000 events
Answer: D
Latest C9560-519 Dumps Valid Version with 70 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments