Based on the SAP Activate methodology, which activities must you perform in the Explore phase?
You reviewed the project scope and identified the corresponding resources.
Based on the SAP Activate methodology, which activities must you perform in the Explore phase? (2 correct)
A . Conduct the Fit-to-Standard workshops to identify fits, gaps, and perceived gaps
B . Use the Quality system to demonstrate SAP Best Practices processes
C . Use the Starter system to demonstrate SAP Best Practices processes
D . Configure the organizational structure and chart of accounts in the system
Answer: B, C
Latest C_S4CMA_2308 Dumps Valid Version with 159 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments
                 
	