Based on the new timeline, what should the project manager do?

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months.

Based on the new timeline, what should the project manager do?
A . Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders
B . Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline
C . Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule
D . Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Answer: B

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments