A solution architect has been tasked with designing a new environment that meets the needs of a growing company, and has obtained this information:
• The current capacity will be exhausted in 180 days, and the new infrastructure must be deployed and in production prior to that.
• The new servers have a 90-day delivery time.
• A data center for disaster recovery has been selected, and it is 20 miles away and connected by MPLS.
• The security team will continue to utilize its current investments and VM Encryption for the new environment.
• The backup team currently uses Data Domain, and reports show an 8:1 compression and deduplication ratio for backups.
Based on the information obtained, which two statements are risks for the new design? (Choose two.)
A . MPLS will be used to connect the two data centers.
B . The Change Advisory Board will approve all changes.
C . Current back up space will not be sufficient if using VM Encryption.
D . The current firewalls will support the additional workloads.
Answer: A,B