At which of the following fundamental test process activity the sufficiency of the testing and the resulting information are assessed?

Testing should provide sufficient information to stakeholders to make informed decisions about the release of the software or system being tested.

At which of the following fundamental test process activity the sufficiency of the testing and the resulting information are assessed?
A . Implementation and execution
B . Requirements specification
C . Evaluating exit criteria and reporting.
D . Analysis and design

Answer: C