At what stage of project integration management would a project manager and project management team typically coordinate the various technical and organizational interfaces that exist in the project?

At what stage of project integration management would a project manager and project management team typically coordinate the various technical and organizational interfaces that exist in the project?
A . Project plan development.
B. Project plan execution
C. Integrated change control.
D. Project quality planning

Answer: A