At what stage of project integration management would a project manager and project management team typically coordinate the various technical and organizational interfaces that exist in the project?

At what stage of project integration management would a project manager and project management team typically coordinate the various technical and organizational interfaces that exist in the project?
A . Project plan development.
B . Project plan execution
C . Integrated change control.
D . Project quality planning

Answer: B