Site icon Exam4Training

At what point in the project is the risk of failing to achieve the project objectives the greatest?

At what point in the project is the risk of failing to achieve the project objectives the greatest?
A . During project planning
B . During the project execution
C . At the project start
D . At the end of the project

Answer: C

Latest PgMP Dumps Valid Version with 452 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version