At what level does the system calculate costs of maintenance orders? choose 1 answer
At what level does the system calculate costs of maintenance orders? choose 1 answer
A . always on header level depending on the maintenance plant
B . always on operation level depending on the order type and the maintenance planning plant
C . on header level or on operation level depending on the order type and the maintenance planning plant
D . on header level or on operation level depending on the controlling view
Answer: C