At the completion of a project, customer agreement cannot be achieved through negotiations, what should the project manager do next?

At the completion of a project, customer agreement cannot be achieved through negotiations, what should the project manager do next?
A . Start the closing phase.
B . Initiate litigation since all work was completed.
C . Explore arbitration.
D . Inform project team members

Answer: C